I'm not sure if this is a bug or this is some other delay, but my intention is to take the snapshot at precisely 03:00 UTC and the schedule settings show this in the DLM settings, and I know snapshot completion time should obviously be after 03:00. However, the 'Started' time listed on the snapshot page in the console says it's 03:36 and the completion event is 03:43, for a snapshot taken with DLM's schedule. What is the point of setting the schedule if it's so off in its start?

질문됨 일 년 전265회 조회
1개 답변
0

Even in the sidebar for the DLM configuration page it says

Schedules can run:
Schedules can be configured to run:

daily at specific times
weekly on specific days
monthly on specific dates or days of the week
yearly at the end or the start of specific months

so much for specific?

답변함 일 년 전

로그인하지 않았습니다. 로그인해야 답변을 게시할 수 있습니다.