Change DMS Type from Full Load to Full Load and Ongoing CDC

0

When I created a DMS Task in the first instance, I chose Migrate existing data. I now want to change it to do CDC as well. There doesn't appear to be an option to modify this. Can anyone confirm that I have to recreate this DMS task? I just want to know before I delete and recreate to make sure I've no option but to do just that. Thought this option to Modify the migration type should be there especially on a testing phase scenario. Thanks.

已提問 2 年前檢視次數 1553 次

1 個回答
2

Hello.

Although mentioned in the documentation below, it is not possible to change the migration type of a DMS task later.
The current situation requires re-creation.
https://docs.aws.amazon.com/dms/latest/userguide/CHAP_Tasks.Modifying.html

You can't change the migration type of a task.